Frees y asfalta caminda di L.G. Smith Blvd

Entrante otro siman diamars dia 11 di april 2023, trabounan di frees y asfalta riba L.G. Smith Blvd (entre turbo rotonde di wendy’s te Ex dow) lo cuminsa.
Trabounan di frees caminda lo wordo haci den fase y nan lo ta:
Fase 1: APA t/m Turbo Rotonde (5 dia)
Fecha di trabou: 11 April t/m 17 April 2023.
Orario: 7:00pm - 1:00am
Fase 2: Entrada dilanti APA (1 dia)
Fecha di trabou: 18 April 2023.
Orario: 7:00pm - 1:00am
Fase 3: Banda Noord Citgo Gas station L.G. Smith BLVD (3 dia).
Fecha di trabou: 19 April t/m 21 April 2023.
Orario: 7:00pm - 1:00am
Fase 4: APA t/m Citgo Gas station @ Tanki Gate 5 (1 dia)
Fecha di trabou: 20 April 2023
Orario: 7:00pm - 1:00pm
Fase 5: Banda Zuid Citgo Gas station L, Smith BLVD (1 dia).
Fecha di trabow: 21 April 2023
Orario: 7:00pm - 1:00am
Asfaltamento lo wordo haci 2 dia tras di otro.
Afaltamento caminda fase 1
Fecha trabou 23 April 2023
Orario: 7:00am -7:00pm
Afaltamento caminda fase 2
Fecha trabou 24 April 2023
Orario: 7:00pm -3:00am
Ruta di desviacion lo wordo indica cu borchi y baricada di aviso.
Por fabor tene cuenta ❗️